The Nigerian National Petroleum Company Limited (NNPC) and contractor parties to Oil Mining Lease (OML) 118 have signed addenda to the production sharing contract (PSC) and dispute settlement agreement (DSA) for the licence.
The contractor parties comprise Shell Nigeria Exploration and Production Company Limited, Esso Exploration and Production Nigeria (Deepwater) Limited, and Nigerian Agip Exploration Limited.
NNPC spokesperson, Andy Adeh, disclosed this in a statement on Monday, describing the development as a major milestone in advancing the Bonga South West/Aparo (BSWAp) deepwater project towards a final investment decision (FID).
The project is expected to attract about $15 billion in investment, with potential lifetime investment estimated at between $15 billion and $21 billion.
NNPC said the execution of the agreements gives effect to the fiscal and commercial terms approved by the Federal Government to support the development of BSWAp.
The development follows President Bola Tinubu’s approval of the Deep Offshore Oil and Gas Projects Incentives (Tax Remission) Order 2026.
According to NNPC, the agreements demonstrate the government’s commitment to creating a stable and competitive environment capable of attracting large-scale investments in Nigeria’s deepwater oil and gas sector.
“The BSWAp PSC and DSA Addenda demonstrate the practical impact of these reforms in translating policy into investment and project development,” the company said.
Project targets 175,000 barrels daily
NNPC said BSWAp is expected to become one of Nigeria’s largest deepwater developments, with projected peak production of about 175,000 barrels of oil per day and 140 million standard cubic feet of gas per day.
The project is expected to boost Nigeria’s oil and gas production while increasing government revenues, foreign exchange earnings, local content development and employment opportunities.
NNPC also said the contractor parties had successfully completed the project’s pre-front end engineering design (Pre-FEED) phase.
The milestone, according to the company, will enable the project to progress towards the front-end engineering design (FEED) phase, subject to the required partner, assurance and governance approvals.
A preferred contractor has also been identified for the project’s Floating Production Storage and Offloading (FPSO) facility following a competitive selection process.
NNPC said the selection would allow the FPSO concept to progress into FEED and support further engineering and commercial work ahead of the FID.
It stressed, however, that any eventual Engineering, Procurement, Construction and Installation (EPCI) contract award would remain subject to all necessary approvals.
NNPC: Project will create jobs, boost local businesses
The national oil company said BSWAp would become a significant deepwater production hub once operational, supporting Nigeria’s efforts to sustainably increase oil and gas output.
It added that the project would generate direct and indirect employment across engineering, fabrication, offshore construction, logistics and operations, while creating opportunities for Nigerian contractors and suppliers.
NNPC Group Chief Executive Officer, Bayo Ojulari, said the signing of the agreements demonstrated the impact of the Tinubu administration’s reforms in converting policy decisions into investments.
“This is about unlocking a major deepwater project and demonstrating that Nigeria has a competitive fiscal framework and a clear pathway for sustainable investment in its energy sector,” Ojulari said.
He added that NNPC would continue working with the Federal Government, project partners and other stakeholders to ensure that BSWAp delivers maximum value to the Nigerian federation and citizens.