Nigeria’s Minister of Works, David Umahi, has taken decisive action against Levant Construction Limited, terminating the company’s contract for its failure to deliver on a critical stretch of the Benin–Sapele–Warri federal highway, a major artery in the country’s transport network.
Speaking after a high-level meeting with contractors, Umahi said the termination followed repeated warnings and a final notice which the contractor allegedly ignored. Despite a parallel intervention by the Edo State Government, Levant reportedly failed to mobilize to the site, leaving key sections of the road in deplorable condition.
“While the [Edo] governor completed a 23km stretch for ₦35bn, Levant simply abandoned its part,” Umahi said, adding that public funds advanced to the company would be recovered, and that the EFCC could be called in if refunds are not made.
Immediate Steps Ordered:
- Termination of contract
- Joint measurement of completed work
- Activation of Advance Payment Guarantee recovery through Levant’s bank
A Tale of Two Contractors: Levant vs. Geld/SKECC
In contrast to Levant, Umahi praised Geld Construction and SKECC for resuming work after renegotiations. The minister noted that the Federal Executive Council (FEC) had approved cost revisions to reflect inflation and a jump in asphalt prices—now ₦30,000/m², up from ₦9,000/m².
“We are seeing movement again. Geld has resumed not just in Delta but also on the Lokoja-Abuja and Itoki–Ikorodu roads,” Umahi said.
Regional Equity in Road Projects: Umahi Pushes Back Against Northern Group Criticism
Amid criticism from some Northern-based groups alleging bias in road project allocations under President Tinubu’s government, Umahi firmly pushed back:
“These claims are malicious and uncharitable. In this ministry, we don’t count regions—we follow inherited contracts, national needs, and urgency.”
Facts on Northern Road Projects (As Shared by Umahi):
- Abuja–Kaduna–Zaria–Kano Road:
- Section I & III: ₦252bn (30% paid)
- Section II: ₦525bn (₦152bn already disbursed)
- Sokoto–Zamfara–Katsina–Kaduna: ₦825bn for 750km
- Borno State Projects: Dangote-funded Tax Credit roads – 49km in Bama, 52km in Dikwa
- Kebbi Dual Carriageway: ₦958bn (second phase pending FEC approval)
- Akwanga–Jos–Bauchi–Gombe Superhighway: Being redesigned to six-lane concrete on Tinubu’s directive
“Under Tinubu’s Renewed Hope legacy projects, the North is receiving 52% of investments, the South 48%.”
The Lagos–Calabar Coastal Highway and Misconceptions
Touching on the controversial Lagos–Calabar Coastal Highway, Umahi dismissed claims that the project was Southern-focused:
“A single lane in Kebbi is costing nearly ₦1tn. When the second lane is approved, it matches the cost of Lagos–Calabar segments.”
He emphasized that infrastructure equity was a cornerstone of President Tinubu’s vision.
Performance Updates: Eleme–Onne Section of East–West Road
Addressing public complaints, Umahi clarified that contractor RCC had improved after a rocky start. Some repaving was happening—not due to poor quality—but to ease traffic around flyovers.
“Let critics verify. We’ve done one carriageway. Any additional asphalt is to facilitate smoother traffic.”
Governors Commended for Stepping In
Umahi expressed gratitude to Governor Sheriff Oborevwori of Delta and Governor Monday Okpebholo of Edo for financing emergency work on federal roads in their states.
“They are doing beautiful work. These governors stepped up where federal contractors failed,” he said.
Conclusion: Road to Accountability and Progress
Minister Umahi’s bold move to terminate underperforming contractors and call for EFCC scrutiny signals a shift toward performance-based infrastructure governance. While regional tensions continue to color perceptions, the administration insists that its road development strategy is needs-driven, not regionally skewed.
With rising construction costs, stronger contractor oversight, and increased state collaboration, the Federal Ministry of Works appears committed to ensuring that President Tinubu’s infrastructure agenda delivers real, measurable impact across Nigeria.