The federal government has inaugurated a N40 billion closed-circuit television (CCTV) control centre for the Third Mainland Bridge in Lagos, aimed at enhancing surveillance, safety and traffic management on the busy bridge.
Minister of Works, David Umahi, inaugurated the facility on Sunday, nearly a year after announcing the installation of surveillance cameras on the bridge to curb suicide attempts and enforce traffic regulations.
Speaking at the event, Umahi said the Tinubu administration inherited critical bridge infrastructure in poor condition when it assumed office in 2023.
“When we came on board in 2023, we met a very terrible Third Mainland Bridge, Carter Bridge and Iddo Bridge, both on the pavement, surface, infrastructure above the water and even infrastructure below the water,” he said.
He explained that President Bola Tinubu subsequently directed a comprehensive re-evaluation and rehabilitation of the Third Mainland Bridge, including the replacement of expansion joints.
“The president therefore directed total re-evaluation and rehabilitation of the surfaces of the Third Mainland Bridge and changing the expansion joints. Lagosians were very happy with the president for that beautiful work, and that work completed and commissioned is still succeeding because of the quality,” Umahi said.
The minister commended China Civil Engineering Construction Corporation (CCECC), the contractor that executed the project, for what he described as quality delivery.
Umahi disclosed that a surveillance boat and two Hilux vans provided under the project would be handed over to the Nigeria Police Force to support monitoring activities on the bridge.
“If they need to incorporate other security agencies, they can do that, but the idea of this project is that we have a lay-by on the bridge, so we view everything going on on this bridge,” he said.
He also raised concerns about excessive speeding on the bridge and urged motorists to comply with traffic laws.
Earlier, the Federal Controller of Works in Lagos, Olufemi Dare, described the CCTV control centre as the first of its kind in Nigeria.
“I doubt if there is any bridge in Nigeria that has what we have deployed here today, where you have CCTV to monitor both the underwater and even the bridge itself,” Dare said.
He said the project includes a surveillance boat, two Hilux vehicles, 240 solar panels, multiple inverters, a 300 KVA transformer, a standby generator and several monitoring screens.
Dare also disclosed that the project includes 1,268 solar-powered street lights and a borehole facility.
According to him, the contract was awarded at a cost of N40.17 billion, with N36 billion already paid to the contractor.
“This is the first level of commissioning. We are still going to come back here to do even for the extension of the bridge, which is about to be completed,” he said.
“We pray that very sooner than later, we will come back to do a full-blown commissioning.”