The Nigerian National Petroleum Company (NNPC) Limited has denied that operational challenges within its gas transportation network are responsible for the recent decline in electricity generation across the country.
In a statement on Friday, Andy Odeh, NNPC’s Chief Corporate Communications Officer, said the network operated by its subsidiary, NNPC Gas Infrastructure Company Limited (NGIC), remained available to support gas deliveries to power plants nationwide.
Odeh said the company’s operational records showed no transportation-related constraints capable of explaining the current reduction in electricity generation.
The clarification followed a November 5 statement by the Nigerian Independent System Operator (NISO), which attributed the decline partly to limited gas availability and reduced water inflows into hydroelectric reservoirs.
NISO had explained that inadequate gas supply was restricting the output of some thermal power stations, while lower water levels were affecting hydroelectric generation.
However, the NNPC maintained that the availability of gas transportation infrastructure should be distinguished from gas production, commercial supply arrangements and actual deliveries to individual power plants.
The company also disclosed that gas production had increased by approximately 10 per cent year-to-date in 2026, attributing the growth to efforts to implement the Federal Government’s gas development and monetisation agenda.
The national oil company called for a coordinated assessment of the entire gas-to-power value chain, including the operational readiness of generating units, maintenance schedules and actual gas consumption by power stations.
It urged gas suppliers, transporters, electricity generators and NISO to review their operational data jointly to identify the specific factors affecting electricity generation.
Zebra News reports that the disagreement over the causes of the generation shortfall comes amid persistent electricity disruptions in several parts of Nigeria.
Earlier, Power Minister Joseph Tegbe identified scheduled maintenance at Egbin Power Station, gas supply challenges and alleged sabotage of transmission lines as factors behind outages affecting Lagos, the Federal Capital Territory and two other states.
Tegbe said affected generating units were expected to return to service in phases, with the first units projected to resume operations within 48 to 72 hours.